Historic District Water Main Improvements Project Update

Posted on: February 13th, 2019 by sabed

Historic District Water Main Improvements Project Update

Installation of new 6-inch water main:

  1. Screven Street-Complete
  2. Meeting Street (from Highmarket Street to Dead End)-Complete
  3. Howard Street.-Complete
  4. Meeting Street and River Road.-Complete
  5. Highmarket Street (from Meeting Street to E. Bay Street).-Complete
  6. Highmarket Street (from Meeting Street to Saint James Street).-Complete
  7. Highmarket Street (from Cannon to Queen)-Complete
  8. E. Bay Street (from Highmarket Street to Prince Street).-Complete
  9. Front Street (From St. James Street to East Bay Street).-Complete
  10. Church St. – 90% of line work completed excluding water services

Paving completed:

    1. Highmarket St. (from Queen St. to Cannon St.). Week of 2/4/2019
    2. Highmarket St. (from St. James to East Bay St.). Week of 2/4/2019

Paving Work Pending:

  1. Front Street (from St. James to East Bay Street) – Wednesday 2/13/19 thru Friday 2/15/19
  2. East Bay Street (From Prince to Highmarket Street) Week of  2/18/19
  3. Church Street (from Broad Street to Cannon Street) TBD

InstaValve Installation Work Pending:

  1. Front St. & St. James St. Intersection -TBD
  2. Front St. & Meeting St. Intersection-TBD
  3. Highmarket St. & St. James St. Intersection-TBD
  4. Highmarket St. & Meeting St. Intersection-TBD
  5. Church Street -TBD